Seismic upgrades for schools

Seismic upgrades at BC’s schools are likely to take a decade longer than originally planned.

Today, Education Minister Peter Fassbender said work on the schools is set to be completed by 2030.

The original 2005 plan said the upgrades were to be completed by 2020.

Of the 339 BC schools that require seismic work, 145 are complete and the remaining 194 are in varying stages of planning and construction.