In an update that was just recently sent out, Coastal Gaslink revealed how much progress they’ve made on their Province wide pipeline project.
As of the end of September, the overall pipeline is 75 percent completed and the company said that they are in a good position to finish 2022 strongly.
Almost all of the project’s major watercourse crossings have been completed and reclamation has reached the final stage of pipeline construction.
Although so far, only sections 1 and 4 of the pipeline have been completely finished.
However, a couple of other sections are relatively close to completion with section 2 being 89.5 percent installed and section 8 being 76.1 percent done.